Battle River REA                    

System Status

 

April 18, 19, 20 & 21, 22 & 23, 2007

 

Status as of Apr 22, 2007 - 20:00 Hrs

 

 

Overview

 

On April 18, 2007 at approximately 11:00 Hrs a snow and ice storm caused major damage to our distribution system.

 

In total we have experienced 20 miles of major line damage to the system this includes between 80 and 100 broken poles. This portion of line will require a complete rebuild of the conductor and the majority of the poles.

 

This storm caused power outages to more than of 600 REA members. After reviewing our data this number has increased to approximately 900 members

 

We have BRREA staff and ten mutual aid/contract crews working on the repairs. These crews are using the traditional line equipment with five Nodwells to support the difficult terrain due to the weather conditions.

 

At the current rate of repair we expect to have the majority of the repairs completed by the end of the day on April 20, 2007. (Updated to End of Day April 21, 2007)

 

BRREA staff have completed inspections on the distribution system to determine the magnitude of the damage.

 

Repairs and restoration to date has been completed to approximately 900 members in the areas identified below

Status: Repairs and restoration including unplanned outages identified today approx. 150

 

Area Detail and Information

 

Camrose East:

            Rebuild is approx. 16 miles of single phase

(12 Miles in one section along Hwy 26)

            Members affected 400

            Estimated repair completed by Apr 21 at 12:00 Hrs

 

Status: Rebuilt Approx 10 miles to date

             Revised schedule for completion to the majority of our members is

    Apr 22 at the end of day

The remaining 35members are scheduled to be restored on Apr 23

 

Roundhill East (Hampton Area):

            This area is down stream from the Round Hill Three Phase       

Repair/replace 5 miles of Single Phase Line

            Members experiencing a power outage 200

            Estimated repairs to be completed Apr 21 by end of day

 

Status: Repaired/replaced 3 miles of Single Phase Line

 Service restored to Approx 50 members

             Estimated repairs to most members was completed Apr 21 by end of day

 The remaining 30 members are scheduled to be restored on Apr 23

 

 

Fort/Chipman/Bruderheim Areas

            Additional damage was identified today, 10 poles require replacement

             Approx 5 miles of line requires major repair

 Members experiencing a power outage 20

             Scheduled for completion Apr 21 by the end of day

 

Status: Repairs complete and service restored to all members on Apr 22 by 16:00 Hrs

 

 

 

 

Power Restoration Area Detail

 

Camrose West

            Repair 1 conductor break

            Members experiencing a power outage 60

            Estimated repair completed Apr 19 by 22:00 Hrs

 

Repairs complete Apr 20

            Service restored to all customers

 

 

Roundhill East: (Main Line)

            Rebuild 0.5 miles of three Phase Line

            A change in the damage was upgraded to 3 miles

Members experiencing a power outage 100

            Estimated repair completed Apr 20 by 12:00 Hrs

 

Line energized Apr 20 by 20:00 Hrs

            Two rural substations energized  

            Service restored to Approx 30 members

 

Bashaw East

            Fortis line damage

            Members experiencing a power outage 20

            Estimated repair completed by Apr 19 22:00 Hrs

 

Repairs complete Apr 19

             Service restored to all customers

 

Bashaw/Ferintosh/Meeting Creek        

Replaced fuses/reset OCR’s

            Members experiencing a power outage 100

            Repair completed by Apr 19 12:00 Hrs

 

Repairs complete Apr 19, 07

             Service restored to all customers

 

Viking Area

            Replaced fuses

            Members experiencing a power outage 15

            Repair completed by Apr 19 01:00 Hrs

 

Daysland

            Replaced fuses

            Members experiencing a power outage 10

            Repair completed by Apr 19 17:30 Hrs

 

Lougheed North

            Rebuild 0.5 miles of single phase line

            Members experiencing a power outage 20

            Estimated repair completed by Apr 21 12:00 Hrs

 

Repairs complete Apr 20

             Service restored to all customers

 

Fort/Chipman/Bruderheim Areas

            Replaced fuses

            Members experiencing a power outage 50

            Repair completed by Apr 19 17:00 Hrs

 

 

  

 

Yours truly,

 

BATTLE RIVER RURAL ELECTRIFICATION

ASSOCIATION LIMITED

 

PER:

 

 

COLLEEN MUSSELMAN,

General Manager

 